Shenzhen Daolong International Logistics Co., Ltd., a highly recommended Chinese freight forwarder, leverages the 27-year industry expertise of its parent company, Shenzhen Sunny Worldwide Logistics. We specialize in the Middle East route and are committed to delivering comprehensive global logistics solutions for air and sea door-to-door transportation. As a leading service provider in the Middle East logistics sector, our core competencies include super-large capacity, extremely fast delivery times, and localized resources. We handle 80% of the air freight orders in the Middle East, establishing ourselves as the ultimate recipient of these shipments.
Contact Now

Service Stories

A True Story Of DL: Shipping A Large Laser Cutter From China To UAE

Alice 2026-11-18 19:12:04

Ziyad, our customer in Dubai, needed a large-format fiber laser cutter shipped by air. After disassembly and packing, the longest piece was the gantry beam. It was packed in a wooden case, 4.2 meters long and 620 kg. The main unit weighed 6.8 tons, and the electric cabinet was 1.6 tons. There were seven packages in total, 20.8 tons. The three packages of the exchange table, material rack and tools were not urgent. We arranged them on the next flight.
Ziyad runs a metal processing workshop in Al Quoz, Dubai. He won an order for curtain walls at an exhibition center. No other shipping method could meet his tight deadline. Air freight was the only choice. He knew clearly that sea shipping would take 50 days. The loss from delay would cost far more than the air freight cost.
When I took this order, I checked the dimension sheet of the seven packages first, not the total weight. For oversized cargo, the number of pallets and freight cost do not depend on total weight. They depend on three things: the longest piece, the heaviest piece, and the piece with the smallest contact base area. The total weight of 12.8 tons looked tough. But the real problem holding back our plan was that 4.2-meter beam.
4.2 meters is an awkward length. The common standard pallet is only 3.18 meters long. It cannot hold this case. If we let it stick out more than one meter, the airline will reject it. We had to use a 20ft pallet. It is 6.06m long and 2.44m wide. This kind of pallet can only go into the main deck of a wide-body full cargo plane. One pallet can carry a little over 9 tons in total.
Oversized cargo shipping is not just booking space. We need to design the loading plan for every single piece. When the goods arrived at our warehouse, we re-measured the size and re-weighed them. The main unit was 6.8 tons after weighing, while the customer declared 6.4 tons. Extra shock pads and steel base were added at the factory, making a 400 kg difference. We sent the weighing video to Ziyad.
Next, we checked the floor load pressure. The 6.8-ton main unit only touched the pallet through four small wood blocks. Its floor load exceeded the airline limit. We made a combined steel and wood base for it. Two No.10 channel steel formed the bottom, with wood blocks and rubber pads on top. The weight spread across a surface of 4.4m long and 0.9m wide, and the load requirement was satisfied.
We also prepared the lashing drawing. It marked each lashing point, how many straps to use, the angle between straps and pallet floor, and the breaking strength of each strap. You cannot tie the straps anywhere you like. The ULD pallet has lashing rings, and the cargo hold floor has lock rails. Every point has a rated load capacity. We calculated the strap quantity following the airline template. Our pallet team finished this drawing, and the airline approved it.
The factory only provided the center of gravity data for the whole machine. We asked them to send separate center of gravity and lifting point drawings for each split part. Without these files, the airline would not sign off. Wrong center of gravity or lifting points means wrong padding and lashing. We submitted all these documents together, and the airline approved on the first try.
Things changed the next afternoon. Ziyad called and said he also needed to ship a chiller together. He planned to buy one locally in Dubai to save cost. But he checked many suppliers. No local chiller matched the cooling parameters of this laser machine. The flow rate and temperature control accuracy were not good enough. The laser could not start without the right chiller.
With this new chiller, the pallet load went from 9 tons to 11.1 tons. Weight was not the big trouble. The chiller had a small base and high center of gravity. If we put it together with the electric cabinet on one pallet, floor load would be over limit again. We changed our plan from three pallets to four. The chiller took one separate pallet. We re-balanced all cargo, recalculated all lashing points and strap numbers. We handed in the updated documents the next morning and got approval at noon.
Loading was done that night. I sent a photo to Ziyad the next day. On the fifth morning, he received the whole set of machines at his workshop. For shipping from China to UAE, it is never easy to handle oversized cargo. And we should never overcharge. If you find the right freight forwarder, the trouble they save for you is worth more than the freight you save.